Project Background & Challenges
The owners of Graysmarsh, a 1.5-square-mile marsh / agricultural
complex, were concerned about potential impacts from several activities
that could reduce flow to the marsh, negatively impacting its productivity
and value. One potential flow-reducing activity was the relocation of
a City of Sequim wellfield; another was the lining of leaking irrigation
ditches.
Solution
Aspect performed a comprehensive surface water and hydrogeologic
investigation to evaluate impacts to this tidally influenced marsh. The
project entailed aggressively gauging the creek and marsh and developing
a detailed water balance for the local watershed. We trained Graysmarsh
personnel in stream-gauging and datalogging techniques. We also worked
closely with Graysmarsh fisheries biologists to identify areas that were
more sensitive to reduced flow.
|